MERA’s Net-Metering Rules let ESCOM customers who generate their own renewable electricity export surplus power to the grid and receive credit on their bill. Kwacha Energy is a MERA-certified Class A1 contractor. We can take you from eligibility check to commissioning, so your system is safe, compliant and approved the first time.
Who can apply
Residential, commercial, industrial, agricultural and mining customers of the distribution utility.
Renewable generation only, such as solar PV.
Systems of up to 500 kW (not exceeding 500 kVA or your main supply breaker rating).
Applicants with no outstanding bills, who own the premises or have the owner’s written permission.
How the credit works
You are billed as normal. Energy exported to the grid earns a credit that offsets the energy component of your bill.
The credit does not offset fixed or grid charges, and ESCOM does not pay cash for exports.
Unused credit rolls over to the next billing period.
Credit is not refunded if you vacate the premises or end the contract.
What we do for you
Eligibility and sizing: We check your site, load and supply against the rules and recommend a system size.
Application package: We prepare the site plan, single-line diagram and equipment details, and help with the standard application form and MERA private generation registration.
Design for grid approval: The utility screens each application against network limits, including generation as a share of the line section’s peak load, fault current contribution and short-circuit ratings. We design to those criteria and support any additional review.
Safe installation: Net-metered systems must be installed and maintained by certified electrical installers. We install the required visibly open, lockable, labelled disconnect switch and anti-islanding protection.
Metering and commissioning: The utility supplies the bi-directional net meter at the customer’s cost. We carry out the commissioning test and support utility witnessing and inspection.
Network works: Where the connection needs transformer, cable, switchgear or line works at 11 kV or 33 kV, we can build them.
What to expect
The utility acknowledges applications within 5 business days and aims to respond within 15 working days of receiving a complete one.
Connection fees and meter costs are paid by the applicant.
After approval, the utility may inspect the facility and requires an annual disconnection test.
Carbon credits are treated as belonging to the customer-generator.
The rules are new and ESCOM is at pilot stage. Contact us to discuss what applies to your site.